Everything you need to know about Toronto’s Ontario Line subway project, from cost to timelines

April 30, 2026

Toronto has started tunnelling on its new subway route. The Ontario Line will open up 15 stops between Exhibition Place, west of downtown, and the old location of the Ontario Science Centre in North York. The project is over 15 kilometres long, with more than half of the line running underground .

The subway is a joint project between the city’s Toronto Transit Commission and the provincial Metrolinx transportation agency.

Ontario Premier Doug Ford said in a Facebook post last week that the Ontario Line will create 40 new connections to existing transit routes, “will put nearly 230,000 people” closer to transit, and will “support 4,700,” new Ontario jobs.

“The start of tunnelling is a historic milestone for the Ontario Line which, once complete, will help cut travel times for commuters across Toronto by 40 minutes,” Ford said in a press release.

Here’s everything you need to know about the Ontario Line.

When will it be completed?

When the Ontario Line was first announced in 2019, Metrolinx estimated it would be completed by 2027 . Now, the transit agency won’t set a firm date for its completion.

“We think we’re still trending towards the early 2030s to be done with civil infrastructure,” Metrolinx CEO Michael Lindsay said at a press conference in February.

After that, the subway line would still need to be tested.

How much will it cost?

The initial proposal for this line set the estimated cost under $11 billion . The total investment for the four major GTA transit projects — the Scarborough extension, the Eglinton Crosstown, the Ontario Line, and the Yonge North extension — was $26.8 billion as of May 2021.

Metrolinx declined to give an update on the cost of the Ontario Line. However, a senior government source told Global News in 2024 that the cost of the Ontario Line project alone had increased to $27.2 billion .

The federal government is contributing more than $4 billion to the project.

How will construction affect traffic?

The construction will cause temporary planned and unplanned road closures on major streets and highways .

Andrew Hope, Metrolinx chief capital officer, said in February at a board of directors meeting that the route has already caused a two-lane closure on the Gardiner Expressway.

The line will include three bridges over the Don River and in February, the Metrolinx CEO also said construction could shut down the Don Valley Parkway.

“These are formidable works,” Lindsay said. “If you think about it, we are building the Bloor viaduct again three times for this project, but these are massive works. We will work with all partners to minimize disruptions to people (and) vehicles on the DVP.”

Beginning Sunday, lanes and sidewalks along the west side of Don Mills Road between Eglinton Avenue East and St. Dennis Drive will close for about five weeks, allowing construction teams to build a new temporary platform. The intersection at Don Mills Road and Gateway Boulevard will be particularly affected through May, as construction starts on a new station

How did construction go on previous transit projects?

The TTC opened Line Five (the Eglinton Crosstown LRT) in February. It runs along Eglinton Avenue and has 25 stations. The Eglinton Crosstown LRT took 15 years to complete following the start of construction, disrupting commuters, local businesses and daily traffic for six years longer than originally planned.

“It goes without saying that this line took much longer to deliver than any of us would have wanted or expected,” Lindsay said in a February Metrolinx board meeting.

The Metrolinx CEO said that their “private sector partner at the time of giving us a bid for this project, underestimated the complexity, the risk, and the challenge,” the Eglinton Crosstown construction would pose to civil infrastructure.

The Line 5 budget was originally set at $11 billion in 2007 but it grew by $2 billion over 15 years. In all, the Ontario government spent $13 billion.

Construction on the new Ontario Line subway began shortly after the completion of Line 5, raising public concern about potential cost overruns and delays.



Unpublished Newswire

 
The government of Canada has announced that it has begun the collection of data for the 2026 Census of Population and the 2026 Census of Agriculture. Here’s what to know. What is the Census? Canada’s census, like those going back thousands of years in various parts of the world, is a collection of information about the population, used to help determine political representation and infrastructure needs. The first Canadian census was taken in New France by its first Intendant, Jean Talon. The recorded population (excluding Aboriginal persons and royal troops) was 3,215. Information was...
May 4, 2026 - 14:59 | Chris Knight | National Post
This morning, Dana, Kailey, and Reem were recognized through the 9-1-1 Children’s Achievement Awards for their bravery and quick actions. Mayor Mark Sutcliffe together with Councillor Riley Brockington, Chair of the Emergency Preparedness and Protective Services Committee, presented them with awards for their courage.    The award, held in partnership with Bell, recognizes youth ages 12 and under who effectively used 9-1-1 in a crisis and helped others. This year’s event falls on Emergency Preparedness Week, which runs from May 3 to 9. Check out our Are You Ready? workbook and...
May 4, 2026 - 14:55 | City of Ottawa - Media Relations / Ville d'Ottawa - Relations avec les médias | City of Ottawa News Releases
OTTAWA — Parliamentary Budget Officer Annette Ryan says key details are missing from the federal government’s spending plans and its comprehensive expenditure review. The PBO released four notes on Monday to assess measures laid out in the Spring Economic Update, which was tabled on April 28. One report highlighted the lack of details on the long-term spending path for defence. Canada has committed to spending $82 billion on defence over the next five years to meet its latest NATO spending pledge of five per cent of GDP, with 3.5 per cent in core defence spending and up to 1.5 per...
May 4, 2026 - 14:50 | Jordan Gowling | National Post